Poland introduces grid connection fees for data centres. How other European countries manage access to power
As more European countries introduce fees and financial guarantees for connecting data centres to the electricity grid, Romania could turn its current regulatory framework into a competitive advantage in attracting investment. Poland’s experience, in a market that Romania frequently uses as a benchmark for digital infrastructure development, shows just how strongly new grid connection requirements can influence investors’ plans.
Access to electricity is becoming one of the decisive factors in data centre development across Europe. Germany, the United Kingdom, Greece and Spain have introduced, or are preparing, financial mechanisms and stricter conditions for allocating available electricity grid capacity. These changes could create opportunities for markets that offer competitive connection terms, sufficient power availability and regulatory predictability.
For Romania, this could be an opportune moment to send a positive signal to international investors. The current framework for connecting large industrial consumers does not impose a standard capacity reservation fee calculated per MW requested, while financial guarantees depend on the technical characteristics of each project. Of course, competitiveness depends not only on connection costs but also on the actual availability of electricity, transmission infrastructure, connection timelines and regulatory stability.
As was noted at a previous edition of DataCenter Forum, ‘the window of opportunity is still open’ for Romania. Recent developments in other European markets could provide another reason to seize this opportunity through a coherent strategy for attracting investment in digital infrastructure.

Poland: From 200 GW of Requested Capacity to Approximately 11 GW
In spring 2026, Poland’s electricity transmission system operator, Polskie Sieci Elektroenergetyczne (PSE), was facing an unusually high volume of grid connection requests for data centres. The total requested capacity had reached approximately 150–200 GW, five to seven times the country’s peak instantaneous electricity demand.
The explanation was relatively simple: developers could apply for connection capacity without initially taking on significant financial obligations. As a result, the operator’s pipeline had accumulated projects at very different stages of maturity, including speculative proposals with no certainty that the investments would go ahead.
The situation changed on 30 April 2026, when amendments to Poland’s energy legislation came into force.
The new regulations introduced two financial obligations for developers seeking a connection to the transmission grid:
An application submission fee of PLN 1/kW, equivalent to approximately EUR 228/MW, capped at PLN 100,000.
An advance payment towards the connection charge of PLN 60/kW, equivalent to approximately EUR 13,700/MW, capped at PLN 6 million.
For applications already submitted, developers were given a transition period in which to meet these financial obligations. Applications for which the required payments were not made were removed from the assessment process.
The impact was immediate. According to figures reported as at 30 September 2026, approximately 11.1 GW remained in the PSE register, comprising 9 GW of projects for which connection conditions had been issued and a further 2.1 GW still under assessment. Compared with the initial 150–200 GW, this represents a reduction of more than 90%.
There is, however, an important caveat. Approximately 7 GW of the remaining capacity reportedly belongs to a single developer, raising questions about the maturity of the overall portfolio and the likelihood that all these projects will be delivered.
A further deadline, 30 October 2026, required certain projects that had obtained connection conditions before the reform to meet the financial obligations as well. Subsequent updates to the PSE register will show how many of these projects retained their positions.
Poland’s experience illustrates just how wide the gap can be between requested electrical capacity and investments with a realistic prospect of reaching construction. Removing applications from the register does not automatically mean that confirmed investments have been cancelled. In many cases, it reflects the withdrawal of development proposals that failed an initial financial test.
Grid Access: A European Challenge
Poland is not the only European country seeking to limit speculative electricity grid connection requests. Rapid growth in demand from data centres, particularly infrastructure dedicated to artificial intelligence, is prompting regulators and transmission system operators to introduce financial mechanisms and stricter criteria for allocating available capacity.
Greece: Guarantees of EUR 200,000/MW for Data Centres
Greece is preparing one of Europe’s strictest sets of rules for data centre grid connections. Draft legislation submitted to Parliament in October 2026 provides for a financial guarantee of EUR 200,000/MW, equivalent to EUR 20 million for a 100 MW project. The guarantee would be reduced by 25% upon signing the connection agreement, while developers would bear the full cost of the required works. The draft also introduces a fee of EUR 2,000/MW for each month by which the capacity reservation is extended, as well as a requirement to source at least 60% of annual electricity consumption from renewables. These measures come at a time when data centre connection requests have exceeded 10 GW, far above the market’s current requirements. As of early November 2026, the regulations were still going through the legislative approval process.
Source: B2Green – New Grid Connection Conditions for Data Centres in Greece
Germany: Application Assessment Fee and Financial Guarantee for Capacity Reservation
In Germany, the four electricity transmission system operators – 50Hertz, Amprion, TenneT Germany and TransnetBW – introduced a new connection application assessment system, known as the Reifegradverfahren, on 1 April 2026. It replaces the first-come, first-served principle with an assessment based on project maturity and likelihood of completion, including for data centres, energy storage facilities and other large industrial consumers.
Under the procedure published by Amprion, each connection application is subject to an assessment fee of EUR 50,000 to cover the costs of evaluation, prioritisation and grid studies. Projects subsequently selected for capacity reservation must provide a guarantee of EUR 1,500/MW. This amount is deducted from the project’s later contribution to infrastructure costs if the project goes ahead, but may be forfeited if the developer abandons the investment for reasons attributable to the developer.
In addition to financial obligations, the assessment takes into account land availability, the status of permits, technical documentation and implementation capacity. Priority is therefore no longer determined solely by when an application was submitted.
Source: Amprion – New Grid Connection Assessment Mechanism

United Kingdom: Proposed Guarantees of Up to GBP 712,500/MW for Data Centres
The United Kingdom is considering a considerably stricter financial mechanism. In July 2026, the regulator Ofgem launched a consultation on introducing a Data Centre Commitment Fee for data centre projects seeking an electricity grid connection. The proposal targets projects requesting at least 40 MW and provides for a guarantee ranging from GBP 237,500 to GBP 712,500/MW, equivalent to 2.5–7.5% of the estimated average investment value. For a 100 MW data centre, the mechanism would require a guarantee of approximately GBP 23.8–71.3 million.
The guarantee would be returned upon commissioning if the developer fulfils its obligations, but could be forfeited if the project is abandoned or implementation milestones are not met.
The scale of the problem helps explain this approach. According to Ofgem, connection requests from large consumers rose from 41 GW to 125 GW in less than a year, with data centres accounting for at least 80 GW of that increase.
As of early November 2026, the mechanism was still under review following the public consultation and had not been definitively adopted as a financial obligation.
Source: Ofgem – Proposed Data Centre Connection Reforms
Ireland: EUR 7,000 Initial Fee and Restrictive Technical Conditions
Ireland, one of Europe’s markets with a high concentration of data centres, applies a connection framework in which administrative costs are accompanied by strict technical and energy-related conditions.
According to the operator EirGrid, applications for a direct connection to the transmission grid require an initial payment of EUR 7,000, including VAT, when the complete documentation is submitted. This represents the first instalment of the application processing fee, whose total amount depends on the size of the project and the required works, in line with the annually approved schedule of charges.
For data centres, grid access also depends on the availability of capacity in the requested area. Current regulations also consider the ability of projects to support the security of the electricity system through generation or storage resources and the integration of renewable energy.
Consequently, paying the assessment fee does not guarantee access to the requested capacity, and actual connection costs are determined on a project-by-project basis.
Source: EirGrid – Demand Connections and Data Centre Connection Procedures
Netherlands: Grid Congestion and Flexible Connection Agreements
In the Netherlands, the main challenge is limited electricity grid capacity in certain regions, affecting both data centre development and other industrial investment.
Grid operators, including TenneT, use congestion management mechanisms and promote flexible connection agreements under which consumers agree to limits on available power at certain times in return for the ability to use existing grid capacity.
Connection costs are determined by each project’s technical characteristics and the infrastructure required. We have not identified a standardised national fee per MW applying exclusively to capacity reservations for data centres that would be directly comparable to Poland’s mechanism. In this case, the emphasis is on making efficient use of available capacity and introducing flexibility in consumption rather than a uniform financial guarantee.
Spain: EUR 40,000/MW Guarantee for Certain Electricity Consumption Projects
Spain provides another relevant example, having introduced financial guarantees for applications for access and connection to the electricity grid. Under Article 23 bis of Real Decreto 1183/2020, introduced for electricity consumption facilities from December 2023, applicants must, in the cases covered by the regulation, provide a guarantee of EUR 40/kW, equivalent to EUR 40,000/MW, before submitting their application.
This obligation applies to consumption facilities within the scope of the regulation, not exclusively to data centres. For a 100 MW project to which the provision applies in full, the guarantee would amount to EUR 4 million.
The guarantee is intended to demonstrate the developer’s commitment and may be adjusted under certain conditions, including where the approved capacity is lower than the capacity requested. The regulation also sets out the circumstances in which the guarantee is returned or forfeited.
Unlike an administrative fee, this amount is a financial guarantee associated with the grid access process
Source: Boletín Oficial del Estado – Royal Decree 1183/2020, Article 23 bis
Romania: What Conditions Apply to Data Centres and Large Industrial Consumers?
As more European countries introduce fees and financial guarantees for reserving electricity grid capacity, Romania could offer data centre investors a competitive advantage through its current connection conditions for large industrial consumers.
Unlike Poland, Romania does not impose a standard capacity reservation fee calculated per MW requested. The process, regulated by ANRE and managed by Transelectrica or the distribution system operators, involves submitting an application, carrying out a grid connection solutions study, issuing the technical grid connection approval (ATR), signing the agreement and completing the required works.
For new electricity consumption sites with an approved capacity of more than 1 MW, ANRE requires a financial guarantee equal to 5% of the connection charge, but only when reinforcement works on the electricity grid are necessary. Therefore, this guarantee does not automatically apply to every project, and its value depends on connection costs determined individually.
An important point for data centre investors is that the increase in financial guarantees to 20%, introduced by ANRE in 2026, does not apply to data centres operating solely as electricity consumption sites. That increase concerns certain electricity generation projects and sites combining consumption and generation. This is a relevant distinction and welcome news for data centre developers, who are not automatically subject to the new financial requirements.
Of course, Romania’s competitiveness also depends on the actual availability of grid capacity, connection timelines and regulatory predictability. Nevertheless, as conditions become more stringent in other European markets, maintaining competitive grid access terms could send a positive signal to international investors.
From Announced Projects to Viable Investments
Poland’s experience is also relevant to Romania, where numerous data centre investments have been announced, including large-scale projects dedicated to AI infrastructure.
However, requested electrical capacity must not be confused with installed IT power capacity or investments that have actually been committed. There are important differences between announced projects, projects that have secured connection conditions and those actually under construction. Poland’s experience shows that introducing financial obligations can dramatically reduce the volume of applications without necessarily meaning that real investments have been cancelled.
For Romania, the challenge is to make the most of this favourable period by offering investors not only competitive financial conditions, but also genuine access to electricity, suitable infrastructure and predictable connection timelines.
The window of opportunity for Romania to develop into a regional data centre market is still open. Recent developments in other European countries provide an additional reason to turn investor interest into concrete projects.
Sources
- PSE – Changes to Grid Connection Rules in Poland
- Ofgem – Measures Against Speculative Data Centre Grid Connection Requests
- ANRE – Amendments to Grid Connection Regulations
- ANRE Order No. 15/2026 – Amendments to the Grid Connection Regulation
- Transelectrica – Access to the Electricity Transmission Grid