Category: News

Poland introduces grid connection fees for data centres. How other European countries manage access to power

As more European countries introduce fees and financial guarantees for connecting data centres to the electricity grid, Romania could turn its current regulatory framework into a competitive advantage in attracting investment. Poland’s experience, in a market that Romania frequently uses as a benchmark for digital infrastructure development, shows just how strongly new grid connection requirements can influence investors’ plans.

Access to electricity is becoming one of the decisive factors in data centre development across Europe. Germany, the United Kingdom, Greece and Spain have introduced, or are preparing, financial mechanisms and stricter conditions for allocating available electricity grid capacity. These changes could create opportunities for markets that offer competitive connection terms, sufficient power availability and regulatory predictability.

For Romania, this could be an opportune moment to send a positive signal to international investors. The current framework for connecting large industrial consumers does not impose a standard capacity reservation fee calculated per MW requested, while financial guarantees depend on the technical characteristics of each project. Of course, competitiveness depends not only on connection costs but also on the actual availability of electricity, transmission infrastructure, connection timelines and regulatory stability.

As was noted at a previous edition of DataCenter Forum, ‘the window of opportunity is still open’ for Romania. Recent developments in other European markets could provide another reason to seize this opportunity through a coherent strategy for attracting investment in digital infrastructure.

Poland: From 200 GW of Requested Capacity to Approximately 11 GW

In spring 2026, Poland’s electricity transmission system operator, Polskie Sieci Elektroenergetyczne (PSE), was facing an unusually high volume of grid connection requests for data centres. The total requested capacity had reached approximately 150–200 GW, five to seven times the country’s peak instantaneous electricity demand.

The explanation was relatively simple: developers could apply for connection capacity without initially taking on significant financial obligations. As a result, the operator’s pipeline had accumulated projects at very different stages of maturity, including speculative proposals with no certainty that the investments would go ahead.

The situation changed on 30 April 2026, when amendments to Poland’s energy legislation came into force.

The new regulations introduced two financial obligations for developers seeking a connection to the transmission grid:

An application submission fee of PLN 1/kW, equivalent to approximately EUR 228/MW, capped at PLN 100,000.

An advance payment towards the connection charge of PLN 60/kW, equivalent to approximately EUR 13,700/MW, capped at PLN 6 million.

For applications already submitted, developers were given a transition period in which to meet these financial obligations. Applications for which the required payments were not made were removed from the assessment process.

The impact was immediate. According to figures reported as at 30 September 2026, approximately 11.1 GW remained in the PSE register, comprising 9 GW of projects for which connection conditions had been issued and a further 2.1 GW still under assessment. Compared with the initial 150–200 GW, this represents a reduction of more than 90%.

There is, however, an important caveat. Approximately 7 GW of the remaining capacity reportedly belongs to a single developer, raising questions about the maturity of the overall portfolio and the likelihood that all these projects will be delivered.

A further deadline, 30 October 2026, required certain projects that had obtained connection conditions before the reform to meet the financial obligations as well. Subsequent updates to the PSE register will show how many of these projects retained their positions.

Poland’s experience illustrates just how wide the gap can be between requested electrical capacity and investments with a realistic prospect of reaching construction. Removing applications from the register does not automatically mean that confirmed investments have been cancelled. In many cases, it reflects the withdrawal of development proposals that failed an initial financial test.

Grid Access: A European Challenge

Poland is not the only European country seeking to limit speculative electricity grid connection requests. Rapid growth in demand from data centres, particularly infrastructure dedicated to artificial intelligence, is prompting regulators and transmission system operators to introduce financial mechanisms and stricter criteria for allocating available capacity.

Greece: Guarantees of EUR 200,000/MW for Data Centres

Greece is preparing one of Europe’s strictest sets of rules for data centre grid connections. Draft legislation submitted to Parliament in October 2026 provides for a financial guarantee of EUR 200,000/MW, equivalent to EUR 20 million for a 100 MW project. The guarantee would be reduced by 25% upon signing the connection agreement, while developers would bear the full cost of the required works. The draft also introduces a fee of EUR 2,000/MW for each month by which the capacity reservation is extended, as well as a requirement to source at least 60% of annual electricity consumption from renewables. These measures come at a time when data centre connection requests have exceeded 10 GW, far above the market’s current requirements. As of early November 2026, the regulations were still going through the legislative approval process.

Source: B2Green – New Grid Connection Conditions for Data Centres in Greece

Germany: Application Assessment Fee and Financial Guarantee for Capacity Reservation

In Germany, the four electricity transmission system operators – 50Hertz, Amprion, TenneT Germany and TransnetBW – introduced a new connection application assessment system, known as the Reifegradverfahren, on 1 April 2026. It replaces the first-come, first-served principle with an assessment based on project maturity and likelihood of completion, including for data centres, energy storage facilities and other large industrial consumers.

Under the procedure published by Amprion, each connection application is subject to an assessment fee of EUR 50,000 to cover the costs of evaluation, prioritisation and grid studies. Projects subsequently selected for capacity reservation must provide a guarantee of EUR 1,500/MW. This amount is deducted from the project’s later contribution to infrastructure costs if the project goes ahead, but may be forfeited if the developer abandons the investment for reasons attributable to the developer.

In addition to financial obligations, the assessment takes into account land availability, the status of permits, technical documentation and implementation capacity. Priority is therefore no longer determined solely by when an application was submitted.

Source: Amprion – New Grid Connection Assessment Mechanism

United Kingdom: Proposed Guarantees of Up to GBP 712,500/MW for Data Centres

The United Kingdom is considering a considerably stricter financial mechanism. In July 2026, the regulator Ofgem launched a consultation on introducing a Data Centre Commitment Fee for data centre projects seeking an electricity grid connection. The proposal targets projects requesting at least 40 MW and provides for a guarantee ranging from GBP 237,500 to GBP 712,500/MW, equivalent to 2.5–7.5% of the estimated average investment value. For a 100 MW data centre, the mechanism would require a guarantee of approximately GBP 23.8–71.3 million.

The guarantee would be returned upon commissioning if the developer fulfils its obligations, but could be forfeited if the project is abandoned or implementation milestones are not met.

The scale of the problem helps explain this approach. According to Ofgem, connection requests from large consumers rose from 41 GW to 125 GW in less than a year, with data centres accounting for at least 80 GW of that increase.

As of early November 2026, the mechanism was still under review following the public consultation and had not been definitively adopted as a financial obligation.

Source: Ofgem – Proposed Data Centre Connection Reforms

Ireland: EUR 7,000 Initial Fee and Restrictive Technical Conditions

Ireland, one of Europe’s markets with a high concentration of data centres, applies a connection framework in which administrative costs are accompanied by strict technical and energy-related conditions.

According to the operator EirGrid, applications for a direct connection to the transmission grid require an initial payment of EUR 7,000, including VAT, when the complete documentation is submitted. This represents the first instalment of the application processing fee, whose total amount depends on the size of the project and the required works, in line with the annually approved schedule of charges.

For data centres, grid access also depends on the availability of capacity in the requested area. Current regulations also consider the ability of projects to support the security of the electricity system through generation or storage resources and the integration of renewable energy.

Consequently, paying the assessment fee does not guarantee access to the requested capacity, and actual connection costs are determined on a project-by-project basis.

Source: EirGrid – Demand Connections and Data Centre Connection Procedures

Netherlands: Grid Congestion and Flexible Connection Agreements

In the Netherlands, the main challenge is limited electricity grid capacity in certain regions, affecting both data centre development and other industrial investment.

Grid operators, including TenneT, use congestion management mechanisms and promote flexible connection agreements under which consumers agree to limits on available power at certain times in return for the ability to use existing grid capacity.

Connection costs are determined by each project’s technical characteristics and the infrastructure required. We have not identified a standardised national fee per MW applying exclusively to capacity reservations for data centres that would be directly comparable to Poland’s mechanism. In this case, the emphasis is on making efficient use of available capacity and introducing flexibility in consumption rather than a uniform financial guarantee.

Spain: EUR 40,000/MW Guarantee for Certain Electricity Consumption Projects

Spain provides another relevant example, having introduced financial guarantees for applications for access and connection to the electricity grid. Under Article 23 bis of Real Decreto 1183/2020, introduced for electricity consumption facilities from December 2023, applicants must, in the cases covered by the regulation, provide a guarantee of EUR 40/kW, equivalent to EUR 40,000/MW, before submitting their application.

This obligation applies to consumption facilities within the scope of the regulation, not exclusively to data centres. For a 100 MW project to which the provision applies in full, the guarantee would amount to EUR 4 million.

The guarantee is intended to demonstrate the developer’s commitment and may be adjusted under certain conditions, including where the approved capacity is lower than the capacity requested. The regulation also sets out the circumstances in which the guarantee is returned or forfeited.

Unlike an administrative fee, this amount is a financial guarantee associated with the grid access process

Source: Boletín Oficial del Estado – Royal Decree 1183/2020, Article 23 bis

Romania: What Conditions Apply to Data Centres and Large Industrial Consumers?

As more European countries introduce fees and financial guarantees for reserving electricity grid capacity, Romania could offer data centre investors a competitive advantage through its current connection conditions for large industrial consumers.

Unlike Poland, Romania does not impose a standard capacity reservation fee calculated per MW requested. The process, regulated by ANRE and managed by Transelectrica or the distribution system operators, involves submitting an application, carrying out a grid connection solutions study, issuing the technical grid connection approval (ATR), signing the agreement and completing the required works.

For new electricity consumption sites with an approved capacity of more than 1 MW, ANRE requires a financial guarantee equal to 5% of the connection charge, but only when reinforcement works on the electricity grid are necessary. Therefore, this guarantee does not automatically apply to every project, and its value depends on connection costs determined individually.

An important point for data centre investors is that the increase in financial guarantees to 20%, introduced by ANRE in 2026, does not apply to data centres operating solely as electricity consumption sites. That increase concerns certain electricity generation projects and sites combining consumption and generation. This is a relevant distinction and welcome news for data centre developers, who are not automatically subject to the new financial requirements.

Of course, Romania’s competitiveness also depends on the actual availability of grid capacity, connection timelines and regulatory predictability. Nevertheless, as conditions become more stringent in other European markets, maintaining competitive grid access terms could send a positive signal to international investors.

From Announced Projects to Viable Investments

Poland’s experience is also relevant to Romania, where numerous data centre investments have been announced, including large-scale projects dedicated to AI infrastructure.

However, requested electrical capacity must not be confused with installed IT power capacity or investments that have actually been committed. There are important differences between announced projects, projects that have secured connection conditions and those actually under construction. Poland’s experience shows that introducing financial obligations can dramatically reduce the volume of applications without necessarily meaning that real investments have been cancelled.

For Romania, the challenge is to make the most of this favourable period by offering investors not only competitive financial conditions, but also genuine access to electricity, suitable infrastructure and predictable connection timelines.

The window of opportunity for Romania to develop into a regional data centre market is still open. Recent developments in other European countries provide an additional reason to turn investor interest into concrete projects.


Sources

wooden cubes spelling 'REIT' on a laptop, with wooden house models in the background, symbolizing real estate investment

Could REITs Unlock Financing for Romania’s Data Center Infrastructure? What Can We Learn from Europe?

Romania has numerous announced data center projects, some with planned capacities of hundreds of megawatts and substantial investment requirements. However, turning these plans into actual investments depends on access to power, customers and, above all, financing. Real Estate Investment Trusts (REITs), a model already used by some of the world’s largest digital infrastructure operators, could offer a solution. As Romania considers introducing a dedicated legislative framework, the experience of other European markets highlights both the opportunities and limitations of this investment structure.

Why Does Romania Need REITs?

Financing real estate investments through specialized investment vehicles is gaining renewed attention in Romania, amid ongoing discussions about introducing a legislative framework for REITs. These structures allow capital to be raised from individual and institutional investors to acquire and manage income-generating assets, such as commercial buildings, logistics facilities or digital infrastructure. Over the past year, the Romanian market has shown growing interest in these investment vehicles, reflected in dedicated events and editorial supplements.

In Romania, developing such a mechanism could have implications extending well beyond the traditional real estate market. One industry that could benefit directly is the data center sector, where initial investments are substantial and capital is typically recovered over long periods.

For companies involved in developing data center infrastructure, financing is a very practical challenge. There are projects and interested investors, including local developers planning to build large-scale data centers, who face difficulties securing bank financing. Introducing a mechanism such as REITs could help unlock these investments and accelerate the development of the domestic market.

In this context, REITs would represent not only an alternative investment option for capital market participants but also a financing instrument for one of the strategic infrastructures underpinning the digital economy.

REIT Legislation Is Still in Parliament. What Could It Change?

Romania already has a draft law dedicated to real estate investment companies (SII), the local equivalent of REITs. Registered as PL-x 433/2024, the bill was adopted by the Senate in September 2024 but remains under consideration by the Chamber of Deputies, the decision-making chamber. According to the legislative record, it received another opinion from the Committee for Industries and Services in March 2026, but the parliamentary procedure has not yet been completed.

The proposed framework aims to enable specialized companies to invest in income-generating real estate assets while benefiting from specific tax treatment and being subject to requirements to distribute profits to shareholders. The version adopted by the Senate includes provisions regarding stock exchange listing, revenue structure and dividend distribution.

For the data center industry, however, the key question is not only when the law will be adopted, but also which types of assets will be eligible for financing through these structures.

A data center is a real estate investment, but its value depends heavily on its technical infrastructure: power supply, cooling systems, redundancy, connectivity and security. Legislation that recognizes only traditional real estate assets could limit the use of REITs in some of the most capital-intensive sectors.

There is another challenge specific to data centers: the obligation to distribute a large proportion of profits must be balanced against the need for reinvestment. Unlike an office building, a data center requires continuous technological upgrades and expansions of its power and cooling capacity.

At the same time, Parliament is also reviewing the government’s draft bill PL-x 544/2026, aimed at modernizing the regulatory framework for investment funds. This is separate from the REIT bill and should not be confused with the introduction of a dedicated tax regime for real estate investment companies.

What Can We Learn from Central and Eastern Europe?

Countries across the region have adopted different approaches. Some already have operational REIT structures, others rely on real estate funds or alternative investment vehicles, while several are still debating the necessary legislation.

Country REIT Status Relevance to Data Centers
Poland No dedicated operational REIT regime yet Growing data center market, but no confirmed local REIT examples
Czechia No REIT regime as such; relies on regulated real estate funds Potential financing through investment funds rather than traditional REITs
Hungary Operational REIT regime known as SZIT Examples of investment in commercial properties, but no established domestic data center REIT model
Bulgaria Operational REIT regime with listed companies Relevant experience in raising capital, but no confirmed data center REIT examples
Serbia Relies on alternative investment funds No REIT regime comparable to those in Hungary or Bulgaria has been identified

Poland: A Large Data Center Market Without Finalized REIT Legislation

Poland is perhaps the most interesting regional market for comparison with Romania. Its data center industry is more developed, and Warsaw attracts significant investment in digital infrastructure. Nevertheless, Poland still lacks a dedicated REIT regime, although its introduction has been discussed for several years.

The proposals under consideration have included listed companies, capital requirements, the distribution of a significant proportion of profits and preferential tax treatment. However, the legislative process has faced challenges, including debates over whether residential properties should be included.

Interestingly, Poland’s data center industry continues to develop independently of a domestic REIT framework. Investments are supported by private capital, institutional financing and international investment structures.

For Romania, the lesson is twofold: REITs are not a prerequisite for data center development, but they could provide an additional financing channel, particularly for local developers who do not have the same access to capital as major international operators.

Hungary: An Established Model for Listed Real Estate Investment

Hungary has an operational REIT regime known as SZIT (Szabályozott Ingatlanbefektetési Társaság), which provides tax benefits to eligible companies.

A concrete example is Graphisoft Park in Budapest, a company listed on the stock exchange since 2006 that has operated under the SZIT regime since 2018. The company develops and manages a real estate park designed for technology companies and research and development activities.

Although it is not a data center operator, Graphisoft Park demonstrates how a listed real estate investment vehicle can attract capital for specialized assets serving the technology industry.

For Romania, Hungary’s experience is particularly relevant because it demonstrates the viability of such a framework in a Central and Eastern European economy. However, the existence of the regime does not automatically guarantee the emergence of a large number of REIT companies or their expansion into digital infrastructure.

Bulgaria: An Established REIT Market in the Region

Bulgaria provides another relevant example, having developed a framework for special purpose investment companies, known as ADSICs.

Several listed companies operate in the Bulgarian market, including Advance Terrafund, Bulgarian Real Estate Fund and Sopharma Properties. Their portfolios include agricultural land, commercial properties and other real estate assets.

Bulgaria’s experience demonstrates that such a mechanism can work even in relatively small capital markets. Investors gain exposure to real estate assets without purchasing them directly, while developers can raise financing through the stock market.

However, no major Bulgarian data center operator explicitly using the REIT model has been identified. This suggests that establishing a legislative framework is only the first step. Financing digital infrastructure also requires sufficiently mature projects, solid commercial contracts and investors familiar with the specific characteristics of the industry.

Czechia and Serbia: Financing Through Alternative Investment Vehicles

Czechia does not have a REIT regime as such, but it has a well-developed industry of real estate funds and funds for qualified investors. These allow property portfolios to be financed and managed through regulated structures, some of which benefit from specific tax treatment.

In Serbia, the framework for alternative investment funds was updated in 2025, with the amendments entering into force in December, bringing local regulations closer to European standards. No dedicated REIT regime comparable to those in Hungary or Bulgaria has been identified.

These two markets demonstrate that infrastructure financing through private capital can involve several types of investment vehicles, not just REITs. The differences lie in accessibility for individual investors, tax treatment, liquidity and the ability to raise capital through the stock exchange.

What About Western Markets? From the US Model to the European Experience

The United States provides the most relevant example of using REITs to finance digital infrastructure. The model has been operating in the data center industry for more than two decades and has supported the development of global operators such as Digital Realty and Equinix. Both companies are publicly listed and use REIT structures to raise capital, finance infrastructure expansion and manage international data center portfolios. The American model demonstrates that REITs can support multibillion-dollar investments in an industry characterized by very high upfront costs, long-term contracts and recurring revenues.

In Europe, the United Kingdom offers one of the most interesting recent examples. Tritax Big Box REIT, a company listed on the London Stock Exchange and initially specializing in logistics properties, has expanded into data center development. In 2026, the company secured approval for a 107 MW project near Heathrow and advanced a second 125 MW project in Chelmsford. Its pipeline of development opportunities exceeds 1 GW, and the company announced plans to raise approximately £350 million through a share issue to finance its expansion.

The British model is also notable for its integration of energy infrastructure. Tritax is working with EDF Renewables to secure access to power, following a power-first strategy in which electricity availability becomes a key criterion for project development.

Germany represents a complementary model, where REIT financing is primarily reflected in investments made by major international operators. Frankfurt, one of Europe’s leading data center hubs, hosts infrastructure developed by Digital Realty and Equinix, both US companies structured as REITs. Digital Realty has a significant data center portfolio in the Frankfurt region, while Equinix operates colocation and interconnection infrastructure for enterprises, telecom operators and cloud providers.

These two European markets illustrate different approaches: in the United Kingdom, a domestic REIT mobilizes capital to develop new projects, while in Germany, international REITs contribute to the expansion of a mature digital infrastructure market.

For Romania, these examples demonstrate that REITs can serve as a mechanism for connecting private capital with data center investments. They can facilitate both the participation of local investors in digital infrastructure projects and the attraction of international capital. At the same time, the British experience highlights a particularly relevant direction for the Romanian market: the convergence of real estate investment, energy infrastructure and data center development.

What Should Future REIT Legislation Allow?

International experience shows that the success of REITs depends on more than tax incentives. Asset eligibility, access to capital markets, corporate governance, transparency and regulatory stability are all essential factors.

For the data center industry, it would be important for Romanian legislation to clarify how technical buildings, associated power and cooling infrastructure, and revenues generated from operating these assets are treated.

A balance must also be struck between distributing profits to investors and preserving companies’ ability to finance the necessary upgrades and expansions.

Romania’s Data Center Infrastructure Market Could Reach USD 800 Million by 2035. Announced Investment Projects Exceed 1.8 GW

Romania’s data center infrastructure market could reach nearly USD 800 million by 2035, driven by the expansion of cloud services, the digitalization of the economy, and growing demand for artificial intelligence infrastructure. At the same time, data center projects publicly announced in recent years point to significant investment potential, with a combined planned capacity exceeding 1.8 GW, according to an analysis conducted by Tema Energy.

According to the Romania Data Center Infrastructure Market report published by DC Market Insights (https://www.dcmarketinsights.com/report/romania-data-center-infrastructure-market) , the market grew from USD 204.34 million in 2020 to USD 346.87 million in 2025, an increase of nearly 70% in five years. By 2035, the report forecasts a market value of USD 794.68 million, representing a compound annual growth rate (CAGR) of 8.57%.

The estimate covers the data center infrastructure market—including power supply and distribution, cooling, racks, associated IT infrastructure, monitoring, and management—rather than the value of commercial services provided by data center operators. Electrical infrastructure represents the largest market segment, while increasing IT equipment densities associated with artificial intelligence are expected to drive further investment in power infrastructure, operational resilience, and advanced cooling technologies.

More Than 1.8 GW of Announced Data Center Projects in Romania

One indicator of the market’s potential is the scale of publicly announced data center projects that have yet to be completed. Tema Energy’s analysis, based on publicly available information, identifies a potential development pipeline exceeding 1.8 GW, divided into two categories.

The first category, totaling approximately 1.46 GW, includes projects for which the investor, location, and planned capacity are publicly known. These include the ClusterPower/AIC developments in Dolj County, WDP/Lamas Invest in Ilfov, Portland Trust in Bucharest, DriverAI/Leviatan in Cluj, SANY International in Timișoara, NIMB in Bucharest, and NXDATA-3 in Tunari.

The second category, totaling approximately 370–375 MW, comprises publicly announced projects for which complete information regarding the location, investor, or development status is not yet available.

These figures represent investment intentions and development plans, rather than contracted or guaranteed IT capacity. The projects are at different stages of maturity, and their announced capacities may refer to IT load, installed power capacity, or grid connection capacity. Even with these qualifications, the scale of the pipeline points to significant potential for market development.

“The data center projects announced in 2025 and 2026 represent a tremendous opportunity for Romania and could fundamentally transform the size of the local market. Romania has a genuine opportunity to attract major investments if it can provide access to power, connectivity, and the ability to rapidly deliver infrastructure that meets international standards. Even if only a handful of these projects materialize, we are talking about investments of several million euros for every MW built, with an economic impact extending across the entire ecosystem: engineering and design, construction, equipment, IT, certification, and operations,” said Mihai Manole, Managing Partner at Tema Energy.

Romania’s growth prospects are also supported by international market assessments. Bucharest ranks 21st in the Savills Power and Place Index Top 30, which evaluates the future potential for data center development across 54 global markets. Meanwhile, the PwC Global Data Centre Outlook forecasts that annual global data center investment will increase from approximately USD 560 billion in 2025 to USD 1.1 trillion by 2030.

DataCenter Forum 2027: Where Investment, Energy, and AI Infrastructure Converge

These developments will set the stage for discussions at DataCenter Forum 2027, scheduled for May 12, 2027, at Face Convention Center in Bucharest.

Now in its ninth edition, the event aims to provide a comprehensive overview of Romania’s data center market and explore opportunities for the country to attract a larger share of European investment in digital infrastructure.

Under the theme “Building the Future of Romania’s Digital Infrastructure Together,” the conference will bring together data center operators, global technology providers, investors, real estate developers, energy companies, and public authorities.

The preliminary agenda includes topics reflecting the industry’s ongoing transformation:

  • Romania’s Data Center Market Landscape: Which projects have been announced, how many have entered construction, and how much new capacity could become operational?
  • Powering AI: Grid access, renewable energy sources, and Power Purchase Agreements (PPAs).
  • From AI Training to Inference: How is demand for computing power changing, and what opportunities does this create for Romania?
  • Data Center REITs: New financing models for data center investments.
  • Efficiency and Sustainability: Technologies to reduce energy and water consumption, alongside public acceptance of new developments.

DataCenter Forum 2027 reflects an increasingly clear reality: data centers are no longer exclusively an IT industry, but a strategic sector at the intersection of energy, investment, technology, and public policy.

Server room. networking concept

From Reporting to Rating: The New European Framework for Data Center Efficiency

The European regulatory framework governing Data Center energy efficiency is entering a new phase. The article we published on DataCenter Forum in March 2025 told a relatively straightforward story: the European Union was introducing mandatory reporting requirements for Data Centers. Operators with more than 500 kW of installed IT power were required to submit data on energy and water consumption.

The developments introduced in 2026 take this framework one step further: the same data will now underpin a common rating system, based on standardized indicators and automatically generated electronic labels.

The new scheme proposed by the European Commission on 21 September is technically significant because it introduces a common set of metrics for assessing Data Center performance across Europe. Until now, operators have reported data on energy consumption, water use and infrastructure performance. The next step is to turn this data into comparable indicators that will also be publicly visible.

According to the timeline presented by the European Commission, the first electronic labels are scheduled to be issued on 15 September 2027 and will be regenerated annually.

From Measurement to Performance Assessment

Data Center efficiency cannot be assessed solely on the basis of total energy consumption. Two facilities with the same IT capacity may have very different performance profiles depending on the efficiency of their power and cooling infrastructure, the source of the energy they use, their water consumption and their ability to reuse waste heat.

This is precisely why the European framework relies on several indicators.

  • PUE – Power Usage Effectiveness measures the ratio between the total energy consumed by a Data Center and the energy actually used by its IT equipment. It is one of the most widely used metrics for assessing the efficiency of physical infrastructure, particularly power and cooling systems.
  • WUE – Water Usage Effectiveness measures water-use efficiency and is becoming increasingly relevant as Data Center cooling is more closely scrutinized in relation to the availability of local water resources.
  • ERF – Energy Reuse Factor introduces a different perspective: not only how much energy a Data Center consumes, but also how much of the resulting waste energy can be reused.
  • REF – Renewable Energy Factor reflects the proportion of electricity supplied from renewable energy sources.

Together, these indicators provide a more comprehensive picture of a facility’s performance than total energy consumption alone.

What Needs to Be Measured Across the Infrastructure

For operators, one of the most important consequences of the new framework is the need for sufficiently accurate and consistent data to calculate these indicators.

This means that monitoring infrastructure becomes an integral part of the Data Center’s operational infrastructure.

Submetering, for example, makes it possible to separate individual energy loads and identify sources of losses or inefficiency. Instead of relying on a single facility-wide metric, operators can monitor the consumption associated with different systems and areas of the infrastructure.

In practice, preparing for the new system involves:

  • separately monitoring IT energy consumption and auxiliary infrastructure consumption;
  • collecting the data required to calculate PUE and WUE;
  • measuring and documenting reused energy;
  • identifying the energy sources used and the share supplied from renewables;
  • maintaining the historical data required for annual reporting;
  • integrating monitoring systems with reporting processes.

Commission Delegated Regulation (EU) 2024/1364 has already established categories of informational, energy, operational and sustainability indicators, and the new framework builds on this foundation.

Cooling Becomes a Strategic Element

One area where the impact of the new requirements may be particularly visible is the cooling system.

As power densities increase, particularly in infrastructure designed for AI workloads, cooling becomes an important factor both in overall energy consumption and in maintaining IT equipment at its intended performance level.

In this context, operators need to view PUE not simply as a reporting metric, but as an outcome of the Data Center’s technical architecture.

Free cooling, optimized operating temperatures, airflow containment, improved chiller and pump efficiency, and the use of liquid-cooling technologies can all significantly alter a facility’s energy profile.

In high-power-density Data Centers, liquid cooling becomes particularly relevant. However, the efficiency of such technology needs to be assessed at system level, rather than solely at the IT equipment level. Liquid distribution infrastructure, heat exchangers, pumps and heat-rejection systems all contribute to total energy consumption.

From PUE to a Multidimensional Assessment

One important consequence of the new system is that a single metric is no longer sufficient to describe the performance of a Data Center.

A low PUE, for example, does not indicate how much water is being used for cooling or whether waste heat is being recovered and reused. Likewise, a high share of renewable energy does not automatically compensate for inefficient energy infrastructure.

By considering PUE, WUE, ERF and REF simultaneously, the assessment becomes multidimensional.

This approach is particularly relevant when designing new facilities. Decisions regarding the cooling system, electrical architecture, electricity sources, waste heat recovery potential and even the location of a Data Center can influence its reported performance over the long term.

The 500 kW Threshold and the Types of Data Centers Covered

The European framework applies to operators of Data Centers with at least 500 kW of installed IT power. It covers several types of facilities, ranging from Data Centers operated in-house by an organization to colocation facilities and multi-tenant environments where several customers share the same infrastructure.

In terms of size, the framework distinguishes between several categories, ranging from 500 kW–1 MW to facilities exceeding 10 MW. Facility size will also form part of the information associated with the rating, allowing the indicators to be interpreted more meaningfully according to the scale of the infrastructure.

This is important because comparisons between two Data Centers need to take into account their architecture, size and the type of workloads they host.

For those wondering how many such facilities there are in Romania, estimates indicate approximately 25–30, enough for the new requirements to have a tangible impact on the local market.

Reused Energy: The Next Step in Efficiency

ERF brings into focus an aspect that has so far received less attention in the operational assessment of Data Centers: what happens to the thermal energy generated by the infrastructure.

In a conventional Data Center, a significant proportion of the energy consumed ultimately becomes heat that needs to be rejected. From an overall efficiency perspective, however, this energy can also represent a valuable resource.

Connecting a Data Center to local district heating networks or using the recovered heat for other applications can improve the overall energy utilization of the infrastructure. Waste heat recovery and reuse should therefore be considered as early as the design stage, rather than treated solely as a subsequent optimization project.

Renewable Energy Does Not Replace Infrastructure Efficiency

REF introduces another dimension into the assessment: the source of the electricity used.

For operators, access to renewable energy and the use of mechanisms such as long-term Power Purchase Agreements (PPAs) can contribute to improving the facility’s energy profile. However, this does not remove the need to optimize the underlying infrastructure.

A Data Center that consumes less energy for the same workload has an inherent structural advantage, regardless of the source of that energy. Infrastructure efficiency and the decarbonization of the power supply should therefore be treated as complementary objectives.

Timeline: 2026 Is the Year for Technical Preparation

For operators, the period between the development of the framework in 2026 and the first generation of electronic labels in September 2027 is relatively short.

The timeline is important:

  • 2023: the Energy Efficiency Directive establishes the general framework;
  • 2024: Commission Delegated Regulation (EU) 2024/1364 introduces reporting requirements for Data Centers with at least 500 kW of installed IT power;
  • March–April 2026: public consultation on the common rating scheme;
  • May 2026: publication of the revised technical version;
  • 2026: implementation of the technical framework and reporting systems;
  • 15 September 2027: first automatic generation of electronic labels;
  • 31 March 2029: first review of the indicators and performance targets.

For operators, the technical message is straightforward: preparation does not begin when the label becomes public. The data underpinning the label must already have been measured, validated and collected beforehand.

What Operators Should Review

Preparation for the new framework can begin with a technical assessment of the existing infrastructure.

First, operators need to determine whether all the required metering points are in place and whether the collected data can be correlated to calculate the relevant indicators.

Second, data quality needs to be assessed, including measurement frequency, consistency, historical records and auditability.

Third, the results need to be linked back to the physical infrastructure. PUE is an indicator; improving it requires changes to the systems that drive energy consumption, including cooling, electrical distribution, UPS systems, pumps, fans and other auxiliary systems.

Against this background, a technical preparation program should include at least the following:

  1. Auditing the metering system and identifying areas where submetering is missing.
  2. Validating the calculation methodology for PUE, WUE, ERF and REF.
  3. Establishing a baseline for current performance.
  4. Identifying the main sources of auxiliary energy consumption.
  5. Assessing the cooling system and opportunities for improving its efficiency.
  6. Analyzing opportunities for waste heat recovery and reuse.
  7. Evaluating renewable energy sources and energy procurement agreements.
  8. Automating data collection and reporting wherever possible.

What Changes for Data Centers in Romania?

For the Romanian market, the challenge goes beyond complying with a European requirement. It lies in operators’ ability to turn operational data into verifiable and comparable technical information.

Data Centers that already have mature DCIM, submetering and energy-monitoring systems in place start from a stronger data infrastructure position. For facilities that still rely on aggregated measurements, the period leading up to 2027 may become an important phase of modernization.

At the same time, the expansion of cloud and AI infrastructure is placing additional pressure on efficiency. Increasing power densities, greater cooling requirements and increasingly demanding power-supply needs mean that design decisions made today can influence operational performance indicators for many years.

From this perspective, the new European system can be viewed less as a simple reporting obligation and more as a framework for standardizing Data Center performance.

A New Definition of Performance

For the European Data Center industry, the transition from reporting to rating represents an important paradigm shift. Until now, the main question was whether an operator could provide the required data. The next question will be what that data reveals about the performance of the infrastructure.

PUE, WUE, ERF and REF will provide a more granular view of how a Data Center uses energy and resources. For operators, this means that efficiency needs to be addressed simultaneously across electrical infrastructure, cooling, water use, waste heat recovery and energy sourcing.

For new projects, these criteria need to be integrated from the design stage. In an industry where computing capacity is expanding rapidly, efficiency is no longer simply an operational characteristic. It is becoming an integral part of infrastructure design, investment decisions and the competitiveness of digital infrastructure.

The first electronic labels are scheduled for September 2027. For operators, however, the most relevant point in time is not 2027 itself, but the preparation period leading up to it.

Why data centre investment is shifting direction in Europe and what Romania could learn from it

Europe’s data centre market is growing at an unprecedented pace, but that growth is no longer happening where it traditionally did. The FLAP-D region (Frankfurt, London, Amsterdam, Paris, Dublin) remains the heart of the sector, but new capital — particularly that linked to AI model training — is visibly shifting towards the periphery: Spain, Portugal, Italy, the Nordic countries, Poland and, increasingly in public debate, Romania.

 

The starting point: FLAP-D is full, but far from obsolete

For almost two decades, Europe’s data centre map has had five capitals: Frankfurt, London, Amsterdam, Paris and Dublin — collectively known by the acronym FLAP-D. This concentration was no coincidence: mature power grids, high fibre density, interconnection hubs (such as DE-CIX in Frankfurt or AMS-IX in Amsterdam) and proximity to financial and corporate markets made these cities the default choice for any operator seeking minimum latency and fast access to customers.

Two indicators published this summer, however, show that the model is under serious pressure:

  • The JLL – EMEA Data Centre Mid-Year 2026 report shows that new development planned for 2026–2028 is shifting significantly towards greenfield projects located away from traditional hubs.
  • An analysis by The Next Web, based on CBRE data, shows even more clearly that only 37% of the new capacity delivered in Europe in the second quarter of 2026 went to the five FLAP-D markets — the remaining 63% went elsewhere.

Importantly, this is not an “exodus” scenario. FLAP-D continues to grow — but the pace of absolute growth in the core markets is being outstripped by growth in secondary and emerging markets.

 

What the JLL report actually shows

The JLL EMEA Data Centre Report is probably the most detailed tool for understanding this trend through the numbers. A few key points stand out:

FLAP-D is growing steadily, but it is no longer where the marginal investment decision is being made. Live capacity across the region reached approximately 3.8 GW by mid-2026, compared with 1.8 GW in 2019 — a doubling in seven years. A further 1.4 GW is under construction and 2 GW is planned. Paris led deliveries in the first half of the year with 72.5 MW, already exceeding its target for the full year, supported by France’s nuclear capacity. London added 49 MW, Frankfurt 45 MW, Amsterdam 16.3 MW and Dublin 11.4 MW.

Vacancy rates are close to historic lows, while divergence between markets is increasing. The average vacancy rate in FLAP-D stood at 6.4% in Q2 2026 — well below the 16.9% peak recorded in 2021, but almost unchanged over the past two quarters. Frankfurt is the tightest market, with only 3.1% of space available — less than half the FLAP-D average. In practice, large contiguous high-density space has become a scarce resource in the core markets, while pre-leasing several years ahead of delivery has become the rule rather than the exception.

The cost of “powered land” (with allocated electrical capacity) has surged. The average price of land with access to power in FLAP-D has increased by 82% since 2021, from €1.24 million to €2.26 million per MW. Primary markets (FLAP-D) now cost 2.3 times more than secondary markets and four times more than tertiary markets.

The most important structural signal is that greenfield investment is rising from 8% to 39% of projects planned for 2026–2028, while the average distance between a hyperscale site and a hub city has increased from 46 km to 175 km. In other words, new projects are not simply moving to the outskirts of cities — they are moving to the outskirts of entire regions, wherever electrical power can be secured quickly.

JLL’s conclusion is nuanced and useful for any strategic discussion: demand is splitting into two different categories. Latency-sensitive workloads (financial applications, enterprise cloud, everyday digital services) remain “anchored” in FLAP-D, where project delivery times can reach 10 years. Large-scale AI model training (100 MW and above), by contrast, does not require minimum latency — it requires rapidly available electrical power, which is becoming increasingly scarce in traditional hubs.

What CBRE and RaboResearch add

Other analyses confirm the picture outlined by JLL, while adding another dimension that is essential to any business analysis: cost is not the only major factor driving relocation — time matters as well.

Analysts at RaboResearch show that, in congested core markets, a new grid connection can take “10 years or more” — compared with significantly shorter waiting times in Belgium, Portugal, Spain, the Nordic countries and Italy. Amsterdam is the most extreme case: Dutch grid operator TenneT has publicly stated that no additional capacity will be available across most of the Noord-Holland region for the next ten years, while the Netherlands has banned hyperscale projects exceeding 70 MW and 10 hectares across most of the country. Frankfurt’s central grid will not see major upgrades before the 2030s, while work on the West London substation (which supplies the London market) is not expected any earlier — which is why a flagship project such as Nscale’s campus in Essex has yet to get underway. The situation is similar in Denmark.

On the cost side, the CBRE analysis confirms JLL’s figures (“powered” land at €2.26 million/MW, up 82% since 2021) and adds useful context: nothing is cheap in absolute terms in the new markets — but everything is cheaper than FLAP-D, which is a different proposition. Under this combined pressure of cost and time, the share of greenfield land has jumped from 8% to 39%.

According to the source, the clearest indicator of relocation comes from the neocloud segment (providers specialising exclusively in AI infrastructure): new capacity contracts reached 420 MW in Q2 2026, compared with just 89 MW a year earlier — an increase of almost 4.7 times, concentrated particularly in the Nordic countries, where renewable energy is cheaper.

The reports cite specific projects that confirm the trend:

  • Spain — installed capacity of 439 MW at the end of 2025, with the Spain DC association projecting approximately 2,537 MW by 2030; Amazon has committed €33.7 billion to the Aragón region alone.
  • Finland — Nebius is building an €8.5 billion, 310 MW site in Lappeenranta.
  • Norway — the Stargate Norway project near Narvik will start with 230 MW powered by hydroelectricity, with a further 290 MW planned.
  • Ireland — the connection moratorium ended in December 2025, but the “price of entry” remains high: proprietary generation (“behind-the-meter”) sized to match the entire grid connection, together with 80% of annual demand being covered by own investments in renewable energy.

 

CBRE confirmation: the market is growing overall, but its centre of gravity is shifting

The Europe Data Centres Figures – Q2 2026 report independently confirms this direction:

  • Europe’s total data centre market is expected to grow by around 20% in 2026, reaching 13 GW of capacity — growth intrinsically linked to AI infrastructure.
  • The hyperscaler self-build segment (Google, Microsoft, Amazon, Meta and others that build their own facilities) is expected to grow by 22% in 2026, reaching 4.3 GW — the seventeenth consecutive year of double-digit growth. Importantly, 70% of this operational capacity is concentrated in just four markets — Ireland, the Netherlands, Sweden and Belgium — evidence that the “old guard” is maintaining its installed base even as new capacity moves elsewhere.
  • Of the nearly 700 MW delivered in Q2 2026 (colocation + self-build), only 252 MW (37%) went to FLAP-D markets, with the remainder going to secondary and tertiary markets.
  • The neocloud segment quadrupled capacity signings compared with the previous year, reaching 420 MW — again concentrated in the Nordic countries, due to the lower cost of renewable energy.
  • Even as secondary markets grow rapidly, overall take-up remains higher than new supply across Europe — the reason being, as CBRE explicitly states, “the lack of available electrical power, which is causing delays in data centre construction”.

CBRE’s overall message is important for any investor or developer: this is not a market that is shrinking or relocating from a weak region to a stronger one — it is a rapidly growing market in which the marginal investment decision is shifting to locations where power is available quickly, regardless of the brand or age of the location.

 

What, then, are the business arguments?

Taken together, the information from the five sources outlines an extremely coherent investment rationale that can be summarised in four factors:

  1. Grid connection time has become the critical variable, not cost. A project that waits 10 years for a connection in Frankfurt or Amsterdam loses the AI race before construction even begins. A similar project in Aragón, Sines or Kouvola can be connected several times faster.
  2. Workloads have bifurcated. Enterprise cloud, financial applications and everyday digital services remain “tied” to hubs because they depend on minimum latency. Large-scale AI model training does not face the same constraint — it can be located wherever sufficient, affordable and rapidly available electrical power exists.
  3. The cost of “powered” land has become a price of entry rather than an absolute barrier. The higher costs (2.3x and 4x) paid to locate in FLAP-D reflect the scarcity of power and space in the core markets — not any structural superiority of those markets for AI workloads.
  4. Countries that align public policy with this logic benefit disproportionately. The examples of Spain (Declaration of General Interest for accelerating projects), Ireland (a specific legal framework for renewable energy linked to grid connection) and Poland (deliberate positioning as a Sovereign Cloud hub) show that the speed of administrative decision-making has become, in 2026, a competitive advantage just as important as the price of land or energy.

Could the same logic apply to Romania?

The question raised by all the data above for the local market is straightforward: if, in Western Europe, capital is shifting from major established hubs (Paris, Amsterdam, Frankfurt) towards locations that are cheaper and provide faster access to power, could a similar shift follow the same logic — this time on a continental scale — from Western towards Central and Eastern Europe?

The arguments supporting this hypothesis are not speculative — they are exactly the same four variables discussed above, applied on a larger scale:

  • Connection time. Romania does not currently face the 10-year waiting queues seen in Amsterdam or Frankfurt. Within the logic described by RaboResearch and CBRE, this is exactly the kind of advantage that has already shifted billions of euros towards Spain, Portugal and the Nordic countries.
  • The cost of land and energy. Structurally, Romania starts from a price level well below that of primary Western European markets — a situation similar to that of Spain or Poland before the current wave of investment.
  • The energy mix. Projects in Romania could rely on nuclear power from Cernavodă, but also on a hydro-solar-gas mix, just as Norway/Finland (hydropower) have already attracted large-scale AI capital.

The market signal has already been visible for several years. As has been repeatedly discussed at DataCenter Forum Romania — organised by Tema Energy — the local industry is openly considering the idea of Romania becoming the “new Norway” of data centres: a historically modest market that could gain a disproportionately strong position through the combination of available energy and a limited window of opportunity. At the May 2026 edition of the event, this was precisely the central discussion: the future of the sector is no longer defined by construction capacity, but by rapid and predictable access to energy — exactly the area where Romania still has room to move.

All the successful examples in Europe (Aragón, Sines, Kouvola, Warsaw) share one common element in addition to lower costs and available energy: active alignment by the state with this economic interest — whether through accelerated permitting procedures (Spain), a dedicated legal framework for energy and grid connection (Ireland), or an explicit public policy position supported by regional offices and partnerships.

The logic of investment relocation described by JLL and CBRE is not specific to Western Europe — it is a universal market logic that will repeatedly seek out the fastest available combination of land, energy and administrative predictability. Structurally, Romania already has the first two elements. If it can secure the third — sustained, coherent alignment around a national interest, without repeated delays — it could genuinely compete for the position currently occupied by Spain or Finland on this rapidly reconfiguring map.

digital blue water drop icon with binary code

Water Consumption in AI Data Centers: Lower Than in Most Industries

The public debate around artificial intelligence’s water footprint has become fixated on a handful of headline-grabbing figures: 700,000 liters of freshwater “lost” while training GPT-3, a potential global water demand of 4.2–6.6 billion cubic meters by 2027, or the nearly 950 TWh of electricity that data centers are expected to consume by 2030 — roughly as much as the whole of Japan consumes today.

The figures are real and come from reputable sources. The problem is not that they are false, but that they are often presented without context: without considering the cooling technology actually being used, without comparison with other industries and, most importantly, without distinguishing between data centers built ten years ago and those being deployed in 2026.

A question of units before anything else

The first layer of dramatization simply comes down to the unit of measurement chosen for reporting.

Virtually every other form of water consumption — by a household, a farm or a factory — is conventionally expressed in cubic meters (m³). A typical household consumes somewhere around 100–150 m³ of water per year, a figure that almost no one perceives as alarming.

Express the same amount in liters — 100,000–150,000 liters — and the impression changes dramatically, even though the actual quantity of water is identical.

This is precisely the mechanism used, intentionally or otherwise, in most articles about AI and water: the figures are almost always reported in liters rather than cubic meters, making them appear three orders of magnitude larger than they actually are when compared with other household or industrial water consumption figures reported conventionally.

The “700,000 liters” used to train GPT-3, for example, translates into 700 m³ — roughly the annual water consumption of 5–7 typical households. It is a real figure, but one with a completely different visual impact from “700,000.”

The choice of unit does not invalidate the underlying data, but it does explain a significant part of the perception of a “crisis” that has taken hold in the public debate — and it is precisely why the aggregated figures deserve to be examined consistently, alongside the actual technologies behind them.

Where the figures come from — and what they leave out

The 700,000 liters associated with training GPT-3 originate from the field’s landmark study, “Making AI Less Thirsty”, conducted by researchers from the University of California, Riverside, and the University of Texas at Arlington

In a subsequent paper, the same research team estimated that global AI-related demand could reach 4.2–6.6 billion cubic meters of water by 2027 — including both direct server cooling, or “on-site” consumption, and the water used by thermoelectric power plants to generate the electricity consumed by those data centers, or indirect “off-site” consumption.

One detail that is usually missing from media coverage is that the underlying figures largely come from data centers built in arid regions of the United States — Arizona, Texas and Nevada — where water stress is already a structural issue and where conventional evaporative cooling has historically been used extensively. These systems rely on open cooling towers that continuously lose water through evaporation during each cooling cycle.

Extrapolating these figures to every data center, regardless of its cooling technology or the region in which it operates, is one of the main sources of confusion in the public debate.

Where the industry is heading: closed-loop, direct-to-chip and immersion cooling

The essential technical distinction is between open-loop and closed-loop systems.

A conventional evaporative cooling tower operating in an open-loop configuration continuously loses water: water evaporates in order to absorb heat, and those losses must constantly be replenished from the public water network or other sources. This is why the average WUE of a “generic” data center has been reported at approximately 1.8–1.9 liters/kWh by The Green Grid and confirmed by the Environmental and Energy Study Institute.

The industry is rapidly moving toward a different model:

  • Closed-loop cooling — the cooling fluid circulates within a sealed circuit and is continuously recirculated, without evaporation through an open cooling tower. The system is filled once during commissioning, after which the water essentially remains within the system.
  • Direct-to-chip (D2C) — cold plates installed directly on the motherboard remove heat from CPUs and GPUs, eliminating the need to cool the entire volume of air inside the data hall. This is becoming the standard solution for the high densities required by AI clusters — racks in the 40–130+ kW range — where conventional air cooling is reaching its physical limits.
  • Immersion cooling — servers are submerged in a dielectric liquid, almost entirely eliminating the need to cool the air within the server room. It is one of the most aggressive approaches in terms of efficiency. Although large-scale adoption is still at an early stage, deployment is increasing in high-density GPU clusters.

The difference is an order of magnitude, not merely a matter of rhetoric.

Microsoft, one of the relatively few operators publishing audited data, reported an average WUE of 0.27 L/kWh in 2025, compared with 2.3 L/kWh in the early 2000s — an improvement of almost 90% over two decades, achieved largely by moving away from industrial chiller-based cooling toward direct evaporative systems and, more recently, toward designs that use no evaporation at all (Microsoft, June 2026).

The company has announced that its new generation of data centers will use zero-water-evaporation closed-loop cooling systems, filled once during construction and recirculated throughout the facility’s operating life (Microsoft Cloud Blog).

The trend is clearly visible across the entire industry. The high-density racks required by AI clusters — 40 kW and increasingly more than 100–150 kW — are effectively forcing the transition to liquid cooling, particularly closed-loop and direct-to-chip configurations, because conventional air cooling is no longer physically capable of removing such heat densities efficiently.

Operators that have already made this transition report reductions in water consumption of up to 80% compared with conventional evaporative systems, while the industry’s focus is shifting from “how much water do we use?” to “how much water can we recirculate instead of losing?”

Alongside direct-to-chip systems, immersion cooling — in which servers are submerged in a dielectric fluid — represents another emerging technology capable of reducing water requirements even further by almost entirely eliminating the need to cool the air inside the server room.

What WUE do Microsoft, Amazon and Google have today — and what are they doing to reduce it further?

The three major hyperscalers report their figures differently, but the direction is the same: WUE is declining, even as absolute water consumption increases with the construction of new facilities.

Microsoft achieved 0.27 L/kWh in fiscal year 2025, down from 0.30 L/kWh the previous year, and officially announced that it had become “water positive” — replenishing more water than it consumed — five years ahead of its 2030 target (Microsoft, June 2026; Data Center Dynamics).

The company says that approximately 90% of its owned fleet in 2025 operated using cooling systems with low or zero water consumption, with water required less than 5% of the time in cooler regions such as Dublin and Amsterdam and up to 40% of the time in hotter climates such as Phoenix.

At its Phoenix facilities, operational adjustments alone — recalibrated temperature set points, real-time weather analysis and periodic audits — delivered a 23% year-on-year improvement in WUE in 2025.

Microsoft also reports the use of recycled or non-potable water at key locations: 74% of consumption in Quincy, Washington; 99% in Singapore; and 79% in San Antonio.

Amazon Web Services published an absolute global water consumption figure for the first time in June 2026 — 2.5 billion gallons, or approximately 9.5 million m³, in 2025 — alongside a WUE of 0.12 L/kWh, the best figure officially reported by a major hyperscaler. AWS compares this with an industry average of 0.84 L/kWh, making its operations approximately seven times more water-efficient (Data Center Dynamics; aggregated analysis by GPUSmith).

AWS also reported a 2% reduction in water withdrawals at sites it directly owns and operates compared with 2024.

Google is the most widely discussed case because it is the only one of the three whose absolute water consumption has risen visibly alongside its AI expansion: 10.9 billion gallons, or approximately 41 million m³, in 2025 — up 34% from 2024 and more than double the 2021 level, according to its Environmental Report 2026 (Axios; Data Centre Magazine).

The company offsets part of this consumption through water-replenishment projects — 7.7 billion gallons replenished in 2025 through 165 projects across 97 watersheds, equivalent to 78% of its consumption, with a target of reaching 120% by 2030.

It is important to put this into perspective: the increase in Google’s absolute water consumption primarily reflects the expansion of installed capacity — electricity consumption at Google data centers increased by 27% in 2024 alone — rather than a deterioration in efficiency per unit of energy consumed. Nevertheless, it is one of the reasons Google remains a primary target of criticism regarding transparency in its reporting methodology.

The pattern across all three companies is consistent: WUE per kWh continues to decline as new facilities adopt closed-loop and direct-to-chip cooling; absolute water consumption can nevertheless increase simply because the number of data centers and the amount of installed power capacity are growing considerably faster than per-unit efficiency can compensate for.

This is a technical distinction that most media articles systematically omit, and it accounts for much of the public confusion surrounding the issue.

Context: who actually consumes large amounts of water?

Compared with other economic activities, even a modern data center using conventional evaporative cooling is far from being one of the largest water consumers — and a facility operating with closed-loop cooling uses even less:

  • Semiconductor fabs consume between 2 million and 10 million gallons of ultrapure water per day, per facility — meaning that a chip already carries a significant water footprint before it ever reaches a server (World Economic Forum).
  • The brewing industry: producing a single liter of beer can require up to 25 liters of water across the entire production chain.
  • A natural-grass football pitch consumes an average of approximately 100,000 liters of water per day for irrigation alone.
  • Golf courses in the United States consume approximately 2.08 billion gallons of water per day for irrigation, compared with approximately 449 million gallons per day used by all U.S. data centers combined for cooling, according to estimates by the Florida Water & Pollution Control Operators Association.
  • Agriculture remains by far the world’s largest consumer of freshwater, accounting for approximately 72% of total freshwater withdrawals according to the latest FAO AQUASTAT 2025, followed by industry at approximately 16% and the municipal sector at approximately 12%.

At an aggregate level, all U.S. data centers combined account for less than 1% of the country’s total water consumption, according to estimates from Lawrence Berkeley National Laboratory — including both indirect consumption through electricity generation and direct consumption through cooling.

Even the more pessimistic projections from the International Energy Agency, which foresee global data center electricity consumption rising from 485 TWh in 2025 to approximately 950 TWh in 2030 — close to 3% of global electricity consumption — do not fundamentally change the order of magnitude.

Even under an accelerated AI-driven growth scenario, the sector remains several orders of magnitude below other industries in terms of pressure on freshwater resources.

What the European industry says about the issue

Independent confirmation of this perspective comes from within the European data center industry itself.

In a position paper specifically dedicated to the subject — “Seeing Through the Mist: Data Centres and Water Usage” — the European Data Centre Association (EUDCA), based on its own industry data, reaches the same structural conclusion.

The report introduces a technical distinction that most public comparisons overlook: the difference between water usage — the total volume of water withdrawn from a source for use — and water consumption — the portion of that water that is not returned to the source because it has been lost through evaporation or contamination.

A closed-loop system may have water usage comparable to an evaporative system, while its actual water consumption can be close to zero because the water is treated and returned to the circuit or source.

This is precisely the distinction that makes many of the “headline” figures presented in the media misleading when water usage and water consumption are treated as synonymous.

In terms of comparative context, EUDCA cites figures similar to those discussed above, but expressed consistently in cubic meters: an average U.S. golf course consumes approximately 431,537 m³ of water per year, compared with 416,395 m³ for an average 1–5 MW data center — equivalent to the annual water consumption of around 1,000 households.

Across Europe as a whole, the European Environment Agency figures cited by EUDCA show that water withdrawals are distributed as follows: 36% for power-plant cooling, 29% for agriculture, 19% for public water supply — including households and tourism — and 14% for manufacturing. Data centers and other “emerging users,” such as hydrogen production, remain within the remaining 2% not covered by these major categories.

From a technical perspective, the report confirms the pattern described above: the average WUE across European colocation facilities was 0.31 L/kWh in 2025, below the 0.4 L/kWh target established under the Climate Neutral Data Centre Pact, while hyperscalers generally report even better performance due to standardized and higher operating temperatures.

Final considerations

The figures circulating in the public debate about the water supposedly “lost” by AI are not fabricated, but they are almost always decontextualized: they originate from studies modeling older infrastructure, located in arid regions and relying on open evaporative cooling.

Although data centers can be significant water consumers at the local level in certain locations, the sector cannot be classified as a water-intensive industry in the same sense as agriculture, power generation or manufacturing.

At the same time, the rapid pace of development across the data center industry requires careful monitoring and transparent reporting of the resources being used, with a clearly stated objective of moving toward near-zero consumption of potable water and significantly greater water reuse.

 

Data Centers Are Entering a New Phase: From Moratoria to Regulations. What Can Romania Learn from the Experience of the United States and Western Europe?

Just a few years ago, competition among states and regions was straightforward: who could attract more investment in data centers. Today, in the world’s most mature markets, the question is no longer whether new data centers should be built, but how they can be developed without placing pressure on power grids, natural resources, and local communities.

An analysis published by Uptime Institute in June 2026—US data center critics pivot from moratoria to regulations, by Rose Weinschenk—shows that the United States is entering a new phase. While many communities have sought to block data center development through moratoria in recent years, the focus is now shifting toward specific regulations that determine who bears the cost of infrastructure and how transparently the impact of these investments must be reported.

The same trend is also visible in Europe.

Why Are These Regulations Emerging?

Artificial intelligence has completely transformed the scale of data centers. New campuses developed for AI workloads consume hundreds of megawatts, equivalent to the energy requirements of entire cities. In many regions, power infrastructure was not designed to accommodate demand on this scale.

As a result, authorities must address a number of legitimate questions:

  • Who finances the expansion of the power grid?
  • How are residential consumers protected?
  • What is the impact on water consumption?
  • How are emissions and energy consumption reported?
  • What economic benefits remain within local communities?

It is no coincidence that these are precisely the issues dominating the legislative agenda in both the United States and Europe today.

The United States: From Moratoria to Rules

The Uptime Institute analysis reaches a clear conclusion: moratoria are losing ground, while regulations are gaining momentum.

Most U.S. states have recognized that data centers represent strategic investments, generating jobs and significant tax revenue. As a result, few administrations still want to block their development entirely.

Instead, they are seeking to establish clear rules.

Oregon and Wisconsin: Developers Must Pay for Infrastructure

Oregon has adopted one of the firmest approaches to power infrastructure.

New projects must bear the full cost of expanding the power grid, preventing those costs from being passed on to the public.

A similar decision was made in Wisconsin, where the regulator required two data center projects to fully fund the cost of the new power infrastructure. The decision is regarded as a precedent for other states.

Texas and Virginia: Protecting Consumers and Reviewing Tax Incentives

In Texas, the debate is focused on two main areas:

  • limiting the impact on energy bills;
  • reassessing the tax incentives granted to the industry.

Virginia, the world’s largest data center market, is moving in the same direction. The state is considering reducing certain tax incentives and introducing mechanisms to ensure that new investments contribute more to the development of local infrastructure.

Illinois, California, and New Jersey: Transparency

Other states are taking a different approach.

Illinois, California, and New Jersey are advancing legislative proposals that require operators to disclose information on:

  • energy consumption;
  • water consumption;
  • carbon emissions;
  • environmental impact.

The objective is to increase transparency and provide authorities with the data required for infrastructure planning.

Maine: A Rejected Moratorium

There are also examples that illustrate this paradigm shift.

In the U.S. state of Maine, the state legislature approved a moratorium on the development of certain large-scale data centers, but the governor vetoed it.

The argument was straightforward: the investment and jobs generated by these projects are too important to the local economy.

The example is relevant to the industry as a whole: rather than imposing moratoria, authorities are seeking to establish the conditions under which data centers can be developed and integrated into existing infrastructure.

Europe Has Already Been Through This Phase

While the debate is highly visible in the United States, Europe encountered the same challenges even earlier.

Ireland—Power Infrastructure Has Reached Its Limit

Ireland has become one of Europe’s leading hubs for hyperscale providers. Its success has been so significant that power grid operator EirGrid warned that the Dublin area could no longer sustain the same pace of development without posing risks to energy security.

Authorities restricted the approval of new grid connections and introduced additional criteria relating to energy efficiency and the integration of renewable energy sources.

New rules have been introduced since 2025: large data centers must secure 100% of their installed power capacity from their own generation sources and demonstrate that at least 80% of the energy they consume annually comes from new renewable energy capacity.

In March 2026, Pure Data Centres opened Europe’s first off-grid campus. It is not connected to the national electricity grid and operates through its own microgrid, initially powered by natural gas but designed to use biomethane and HVO fuel.

The Netherlands—From Enthusiasm to Strict Rules

The Netherlands has undergone a similar shift.

Following a temporary moratorium on hyperscale projects, authorities introduced strict criteria governing data center locations, energy consumption, land use, and the impact on local communities.

Development continues today, but under far more restrictive conditions than just a few years ago.

Meta’s Zeewolde project remains the best-known European example. Although local authorities had approved the development of the hyperscale campus, public opposition over energy consumption, the use of agricultural land, and limited economic benefits prompted Meta to abandon the investment.

What Do the United States and Europe Have in Common?

Although their approaches differ, the overall direction is the same.

It is no longer enough for a data center simply to bring investment. Operators must demonstrate that they:

  • do not pass infrastructure costs on to the public;
  • use energy and water efficiently;
  • report their environmental impact transparently;
  • contribute to the development of local communities.

In practice, the debate has shifted from “whether to approve construction” to “who pays the costs of development.”

Mature markets are approaching saturation. Virginia, Dublin, Amsterdam, and Frankfurt have one thing in common: they have attracted massive investment for more than a decade and are now facing shortages of available land, difficulties in securing power, increasingly complex permitting procedures, and, above all, opposition from local communities.

Romania Has an Opportunity It Should Not Miss

This situation brings Romania’s opportunity back into focus.

Compared with Europe’s major data center hubs, Romania is starting from a different position.

It still offers several important advantages:

  • available capacity for infrastructure development;
  • competitive costs;
  • excellent connectivity to Central and Eastern Europe;
  • a strategic location on the Black Sea;
  • significant potential to expand renewable energy generation.

In addition, AI-driven demand is creating opportunities for the development of new campuses dedicated to HPC, AI inference, and regional cloud services.

As expanding capacity in Western European markets becomes increasingly difficult, Romania could become one of the natural destinations for the next wave of investment.

But This Opportunity Also Requires Clear Rules

Precisely because Romania is at a different stage of development, now is the right time to define a predictable legislative framework capable of reducing potential friction among investors, utility operators, and local communities.

A modern regulatory framework could provide both investors and local authorities with the clarity required for long-term development.

Such a framework could include:

  • clear rules governing connections to the power grid;
  • mechanisms through which developers contribute to the cost of new infrastructure;
  • reporting standards for energy and water consumption;
  • independent environmental impact assessments;
  • incentives for the use of renewable energy and the recovery of waste heat;
  • transparent mechanisms for dialogue with local communities.

The experience of the United States and Western Europe sends a very clear message: data centers are no longer viewed solely as technology investments, but as critical infrastructure that must be responsibly integrated into the energy and urban ecosystem.

Mature markets have reached a point at which development is constrained by infrastructure and public acceptance. Romania has not yet reached that point, and this represents a major competitive advantage. Romania should not copy the Irish or Dutch model, but instead take advantage of the fact that it is still in a growth phase and can establish clear rules early on.

Climate Risk Becomes a Strategic Factor in the Data Center Industry—Including Europe

Climate Risk Becomes a Strategic Factor in the Data Center Industry—Including Europe

The global race for computing capacity is no longer being played out solely on the grounds of power availability, land supply, and permitting speed. An increasing number of digital infrastructure investors, developers, and operators are bringing a fourth decision-making factor to the table—one that until now was treated as a secondary risk: climate exposure.

This is the central message of the latest report published by First Street, a firm specializing in climate risk analysis, titled “18th Risk Assessment – Climate Risk in Global Data Center Markets”. The study analyzes 97 investable data center markets globally and reaches a conclusion that is hard to ignore: climate risk is no longer a “what-if” scenario, but a variable already integrated into the operational performance of current digital infrastructure.

According to the report:

  • Approximately 54% of global data center capacity operates in markets exposed to chronic climate stress (extreme heat or drought).
  • 79% faces significant acute risks—such as flooding, extreme winds, or wildfires.

Practically, the vast majority of the world’s digital infrastructure is already operating under some form of climate pressure, whether gradual or episodic.

Chronic vs. Acute Risks: The Financial Difference

  • Chronic risks erode margins through higher energy and water costs, as well as reduced cooling efficiency.
  • Acute risks introduce volatility through downtime, repair costs, and skyrocketing insurance premiums.

Both ultimately reflect on Net Operating Income (NOI) stability and asset financing conditions.

How Risk is Distributed by Region

The report’s data maps out a geographically differentiated landscape of risk:

Region Chronic Exposure (Heat/Drought) Acute Risks (Floods/Wind/Wildfires)
Asia-Pacific (APAC) 89% of capacity exposed 60% of capacity exposed
North & Latin America 50% of capacity exposed 86% of capacity exposed
Europe, Middle East & Africa (EMEA) 46% of capacity exposed 25% of capacity exposed

The report identifies specific hubs that sit simultaneously in the high-risk zone across both dimensions. Johor (Malaysia), Singapore, Marseille, and the US state of Virginia are among the markets with the highest combined exposure. Conversely, Nordic cities like Stockholm, Oslo, or Copenhagen remain at the bottom of the risk rankings, benefiting from cooler climates and access to clean energy.

The authors’ conclusion carries direct implications for investment strategies: some of the world’s largest and fastest-growing data center hubs are being built precisely in the areas with the highest climate risk, rather than the safest ones.

Europe: Caught Between AI Ambitions and Climate Goals

Beyond First Street’s data, the climate risk debate directly intersects with a broader discussion gaining momentum in Brussels: Can Europe achieve its technological sovereignty goals in AI without compromising its climate commitments?

Lex Coors, President of the European Data Centre Association (which represents giants like Microsoft, Google, and Amazon before the EU, alongside European players like Digital Realty/Interxion, EdgeConneX, and LCL Data Centers), recently stated that the European power grid is not yet ready to power the next-generation data centers required for AI. Furthermore, Small Modular Nuclear Reactors (SMRs) will not be available in time. In this context, he suggested that the discussion regarding a potential temporary return to gas-fired power plants should at least be opened.

The European Commission aims to triple the bloc’s data center capacity by 2032 as part of its “AI Continent Action Plan”. The issue, according to industry voices, is that the expansion of grids, green energy capacities, and advanced nuclear projects is failing to keep pace with this growth rate.

On the other hand:

  • Commission officials have signaled that data centers are only welcome in Europe if they actively contribute to the energy transition—by supporting renewable capacities and waste heat recovery.
  • Environmental organizations like Greenpeace EU warn that expanding gas capacity would lock Europe into an energy dependency it is already actively trying to eliminate.

The tension is real and lacks a simple solution for now: competitiveness, sovereignty, sustainability, and speed are four objectives that currently cannot be maximized simultaneously.

And in Romania?

While the discussion on the climate risk of digital infrastructure has already reached public and investment agendas in Western Europe, the conversation in Romania remains much quieter.

Romania was not included in First Street’s analysis—a sign that the local data center market does not yet possess the critical mass of capacity required to appear on the radar of global institutional investors. However, the closest analyzed market in the region, Polonia, has its chronic risk level (heat/drought) evaluated in the 25-50% band. This represents a moderate risk—well below top markets like Johor, Singapore, Marseille, or Virginia, but also above the lowest-risk Nordic markets. Effectively, the Central and Eastern European (CEE) region sits somewhere in the middle of the global ranking—neither in the danger zone nor in the maximum climate safety zone.

In Romania, there is currently no real regulatory or local market pressure forcing the integration of climate risk into data center site selection decisions. Compared to the markets analyzed by First Street—where climate has already become an underwriting criterion alongside power costs and connectivity—the topic remains largely peripheral in Romanian public discourse.

The Corporate Divergence

However, things look different for major market players. International operators and large digital infrastructure companies present locally broadly follow the global agendas of their parent organizations:

  • Aiming for near-100% access to green energy.
  • Reducing carbon footprints.
  • Rigorous ESG reporting.

This is driven less by a locally perceived climate risk and more by global corporate commitments, financing requirements, and European regulations (such as the data center sustainability label currently being developed by the European Commission).

The Bottom Line for Romania: A discrepancy is visible. Physical climate pressure, in the strict sense defined by First Street (extreme heat, drought, floods, wind), is still low compared to markets like Johor, Marseille, or Virginia. However, compliance and sustainability pressure coming from investors and European regulations is already present and will continue to escalate.

In the medium term, as regional data center capacity expands—fueled by growing demand for cloud and AI services—climate risk will likely become highly relevant for the local market. This will not necessarily be triggered by immediate extreme weather events, but because the financing, insurance, and valuation of these assets will increasingly depend on climate standards imposed at the European level.

 

Will Energy and Grid Access Limit the Growth of the Data Center Market in Romania?

The Data Center industry appears to be “booming” globally, fueled by billions in investment aimed at satisfying the computing needs and cognitive capabilities of major Cloud and AI players. AI “factories” and data centers swallow tens of thousands of chips, placing immense pressure on manufacturers like Nvidia and turning hardware availability into a project slowdown factor. To secure this aspect, Amazon recently signed a contract with NVIDIA to acquire over 1 million processors by the end of 2027.

But is this the primary obstacle facing the industry? Alexandru Chiriță, CEO @ Electrica, offers a very compelling perspective on a potential AI crisis generated not by a lack of silicon, but by a lack of energy and grid access. This is a topic we will further explore at DataCenter Forum 2026.

“The world’s most capital-rich industry is being bottlenecked by the world’s most capital-starved one: the electric grid.”

The conventional framing of AI’s energy appetite treats it as a demand-side problem: build more power plants, string more cables. This framing is dangerously incomplete. What we are witnessing is a structural collision between the tempo of digital capital and the tempo of grid infrastructure. Hyperscalers can site, permit, and build a data center in 12–18 months. A new transmission line takes 7–12 years. A nuclear plant, 10–15 years. This temporal mismatch isn’t a bottleneck to be optimized—it’s a systemic risk that will reshape where AI gets built, which grids get reinforced, and which countries win or lose the next industrial cycle.

The current situation is well-known in the market; even if data centers are not the most energy-intensive sector, they remain the one with the highest growth in consumption.

Current Scale

  • Global Consumption: Data center electricity consumption reached approximately 415 TWh in 2024 (~1.5% of global demand). This figure has been growing at 12% per year over the last five years—roughly triple the rate of global electricity demand growth.
  • Near-term Trajectory: The IEA projects global consumption will nearly double to 945 TWh by 2030 (equivalent to Japan’s entire national demand). London-based Energy Intelligence estimates demand could reach 1,000 TWh as early as 2026.
  • The AI Multiplier: Facilities once designed for 6–12 kW per rack are now being engineered for significantly higher loads. AI training clusters demand dense, concentrated power blocks that must be provisioned upfront—a pattern fundamentally different from the gradual, predictable load growth grids were designed to serve.

Pipeline Pressure

Over 8.9 GW across 105 European projects are targeting operation by the end of 2026. The constraint is not capital, not land, and not even chips—it is grid connection capacity.

Alexandru Chiriță argues that we are at the point “Where Infrastructure Meets Its Limits.” Countries like Ireland, Germany, or the Netherlands are already in this scenario, forced to slow the momentum of their data center industries:

  • United States: Demand is projected to reach 260 TWh by 2026. Projects from Virginia to Texas are stalled as power grids approach their limits.
  • Ireland: The most extreme case. Data centers already consume 21% of national electricity. A four-year grid connection moratorium (2021–2025) turned the country into a laboratory for what happens when digital demand outpaces physical infrastructure.
  • Germany & Singapore: Both are experiencing connection delays or have imposed strict efficiency requirements and moratoriums to manage the load.

The Romanian Context: From Periphery to Strategic Asset

Romania stands at a remarkable inflection point. The same grid constraints stalling hyperscaler projects in Dublin or Frankfurt could become Romania’s competitive advantage—if the country plays its cards right.

Our Advantages Are Real:

  • Energy Diversity: Clean sources (hydro, nuclear, wind, solar) already provide over 60% of Romania’s electricity. Nuclear alone contributes ~20%—a baseload asset that hyperscalers increasingly demand.
  • Strategic Location: A digital bridge between Western Europe and the Black Sea, supported by an IT workforce of over 200,000 professionals.
  • Grid Expansion: Transelectrica’s 10-year development plan (2024–2033) involves ~€1.9 billion in investment. New grid allocation rules for 2026 are specifically designed to accelerate renewable and large-load connections.
  • Renewable Pipeline: Over 60 GW of approved renewable projects—a massive reservoir of “clean electrons.”

But Our Challenges Are Equally Real:

  • Grid Readiness: Romania’s SAIDI (interruption index) remains around 240 minutes annually, far above the 40–150 minute range of Germany. Hyperscalers demand “five-nines” reliability (99.999%).
  • Absorption Capacity: The 60 GW of approved renewables exceeds actual grid capacity. At least 4 GW of storage will be needed by 2030.
  • Execution Risk: In 2025, Romania’s data center IT capacity was just 77 MW (compared to Germany’s 4,260 MW). Scaling requires institutional speed, not just capital.

The Strategic Question

Romania is not competing with Dublin for yesterday’s market. It is positioning for tomorrow’s: AI-native infrastructure that needs clean baseload power, land, and regulatory willingness. Saturated countries are now deflecting demand; Romania can absorb it.

The question for Romanian energy leaders isn’t whether data centers will come. It’s whether our grid, our regulatory framework, and our institutional speed can match the tempo of the opportunity arriving at our door.

Read the full text directly on LinkedIn: Link to Alexandru Chiriță’s Article

Energie, baterii și centre de date: modelul integrat prin care Monsson vrea să transforme hub-urile energetice în poli digitali

Industria centrelor de date traversează un moment similar cu cel al energiei regenerabile de acum două decenii: un val tehnologic accelerat, nevoia de capital semnificativ și un cadru de reglementare care trebuie să țină pasul cu investițiile. În acest context, Monsson mizează pe un model integrat – energie regenerabilă, stocare prin baterii (BESS) și centre de date co-locate – pentru a poziționa România pe harta europeană a infrastructurii critice pentru AI și cloud.

În acest interviu, Sebastian Enache, Head of M&A Monsson, explică lecțiile învățate din dezvoltarea pieței regenerabile, rolul stocării în susținerea consumatorilor mari de energie și ambiția companiei de a dezvolta o platformă scalabilă de centre de date de până la 200 MW în mai multe regiuni strategice ale țării.

Ca informație colaterală, Sebastian Enache va fi prezent și pe scena DataCenter Forum 2026, în cadrul unui panel care va contura similitudinile și sinergiile dintre sectorul energetic și cel al centrelor de date.

 

DataCenter Forum: În energie regenerabilă, România a trecut prin etape de maturizare și standardizare. Ce lecții din dezvoltarea pieței de energie regenerabilă considerați că ar putea fi aplicate industriei de centre de date locale, mai ales în ceea ce privește autorizarea și integrarea în rețea?

 

Sebastian Enache, Head of M&A Monsson: În energie regenerabilă, România a început să construiască încă din 1999 o direcție strategică, iar în 2003 au fost instalate primele turbine eoliene de capacitate mare pentru acea vreme. Deși existau discuții și despre parcuri fotovoltaice, tehnologia solară nu era atunci suficient de performantă și competitivă, astfel că prioritatea a fost acordată eolianului, soluția cea mai eficientă în acel context. După aproape 25 de ani, vedem că ambele tehnologii au evoluat semnificativ, sunt standardizate, bancabile și aproape la fel de răspândite.

Lecția principală este că orice val tehnologic are momente critice, strategice, în care cadrul de reglementare, capacitatea administrativă și curajul investitorilor fac diferența dintre stagnare și accelerare. La începutul anilor 2000, toată lumea vorbea despre regenerabile, însă puțini aveau experiență reală, legislația era incompletă, iar procesele de autorizare erau neclare. Doar câțiva investitori curajoși au ales să intre într-un domeniu încă nematurizat, asumându-și riscuri semnificative.

Astăzi văd o paralelă evidentă cu industria centrelor de date. Dacă în regenerabile vorbim despre echipamente mari, cu durată de viață de 20–40 de ani, care trebuie să producă energie în mod stabil și predictibil, în zona de data center discutăm despre o infrastructură critică, la fel de complexă și gândită pe termen lung, dar care găzduiește tehnologii ce se schimbă la 2–3 ani. Serverele pot fi înlocuite relativ rapid, însă infrastructura energetică, de răcire și conectivitate rămâne o investiție pe termen lung și necesită predictibilitate legislativă și operațională.

Din experiența regenerabilelor, o lecție esențială pentru centrele de date este importanța unui proces de autorizare clar, coerent și digitalizat, precum și a unei strategii transparente de integrare în rețea. Lipsa de coordonare între investitori, operatori de rețea și autorități poate întârzia proiecte critice ani de zile. În schimb, planificarea anticipată a capacităților de rețea și definirea unor zone prioritare de dezvoltare pot accelera investițiile și reduce riscurile.

Consider că există o convergență naturală între cele două industrii. Profesioniștii din zona centrelor de date trebuie să colaboreze activ cu autoritățile, nu doar pentru a evidenția importanța acestor investiții, ci și pentru a contribui la definirea unui cadru legislativ adaptat realităților tehnologice. Construcția rapidă, conectarea eficientă la rețea și amplasarea în zone adecvate, cu infrastructură energetică robustă, sunt elemente critice pentru ca România să valorifice acest nou val de dezvoltare, așa cum a făcut, în cele din urmă, și în domeniul energiei regenerabile.


DCF: Există un mare interes la Data Center Forum pentru investiții durabile. Cum vedeți rolul stocării de energie (BESS) și sursele regenerabile în susținerea operațiunilor unor centre de date cu consum intensiv – de exemplu pentru AI sau cloud – în România și Europa?

 

Sebastian-Enache

Sebastian Enache: Interesul pentru investiții durabile în zona centrelor de date este firesc, mai ales în contextul creșterii accelerate a consumului generat de AI și cloud. Din perspectiva mea, stocarea energiei prin baterii (BESS) și sursele regenerabile vor juca un rol esențial în susținerea acestor operațiuni în România și în Europa.

Tehnologia BESS este relativ nouă la scară largă, însă în ultimii 5 ani a cunoscut o dezvoltare spectaculoasă, atât din punct de vedere tehnologic, cât și economic. Dacă în trecut integrarea unui sistem de stocare nu era fezabilă financiar pentru majoritatea proiectelor, astăzi aproape toate parcurile eoliene și fotovoltaice moderne includ BESS, iar în paralel vedem dezvoltarea de sisteme stand-alone dedicate serviciilor de sistem. BESS nu mai este doar un accesoriu, ci un element care oferă flexibilitate, stabilitate și predictibilitate rețelei.

În acest context, paralela cu centrele de date este evidentă. Până recent, BESS nu era perceput ca o componentă esențială pentru un data center, unde accentul era pus pe redundanță clasică – generatoare diesel și UPS-uri. Însă, pe măsură ce consumul crește și volatilitatea prețurilor energiei devine o realitate, sistemele de stocare vor deveni, în opinia mea, o componentă standard. De ce? Pentru că permit optimizarea costurilor, prin achiziția de energie la prețuri reduse în perioadele de surplus și utilizarea acesteia în intervalele de vârf. În același timp, oferă o sursă suplimentară de redundanță și pot susține integrarea directă a producției regenerabile locale.

Mai mult, BESS facilitează conectarea eficientă a unui centru de date la un mix energetic verde, reducând impactul asupra rețelei și crescând stabilitatea operațională. Pentru centrele de date AI, unde cererea de putere este mare și constantă, combinația dintre regenerabile, stocare și un management inteligent al energiei poate face diferența între un proiect bancabil și unul vulnerabil la riscuri de preț și disponibilitate.

Viziunea Monsson este clară: un centru de date este mai bine poziționat lângă un hub energetic regenerabil, integrat cu capacități de stocare, decât ca un consumator izolat în rețea. Prin corelarea investiției inițiale în producție și stocare cu profilul de consum al centrului de date, randamentul global al proiectului poate crește semnificativ – estimările noastre indică un potențial de peste 25%. În acest fel, sustenabilitatea nu este doar un obiectiv de imagine, ci devine un avantaj competitiv real.


DCF: Monsson este cunoscută în principal pentru proiectele din energie regenerabilă și stocare. Ce v-a determinat să vă extindeți spre infrastructura de centre de date și ce sinergii vedeți între aceste două industrii? (Mă gândesc la un modelul integrat de energie + baterii + centre de date)

 

Sebastian Enache: Știu, Monsson este cunoscută în principal pentru dezvoltarea de proiecte în energie regenerabilă și stocare, însă extinderea către infrastructura de centre de date reprezintă o evoluție naturală a viziunii noastre. Așa cum am menționat anterior, obiectivul nostru este să atragem cât mai mult consum energetic relevant în proximitatea hub-urilor noastre de producție. Credem că viitorul aparține modelului integrat – energie + baterii + centre de date.

În esență, secretul constă în a aduce consumul lângă producție. În modelul clasic, energia este produsă într-o zonă, transportată pe distanțe mari și consumată în altă parte, ceea ce implică pierderi, costuri ridicate de racordare și presiune suplimentară asupra rețelei. Prin poziționarea centrelor de date în apropierea parcurilor eoliene și fotovoltaice, integrate cu sisteme BESS, putem optimiza întregul lanț investițional. Reducem costurile de infrastructură de transport, scădem timpul de implementare și creăm un ecosistem energetic mult mai eficient.

Pentru dezvoltatorul de centre de date, avantajul este unul strategic: acces la energie competitivă, predictibilă și, din ce în ce mai important, verde. Pentru noi, ca dezvoltator de capacități regenerabile și stocare, integrarea unui consumator mare și constant precum un data center crește stabilitatea financiară a proiectului și îmbunătățește randamentul investiției. Practic, vorbim despre o optimizare suplimentară a investiției tuturor părților implicate.

Sinergiile sunt evidente și din perspectivă tehnică. Bateriile permit echilibrarea producției regenerabile și adaptarea la profilul de consum al centrului de date. În același timp, centrul de date oferă un consum relativ stabil, ceea ce ajută la monetizarea proiectelor energetice. Într-un astfel de model, rețeaua națională devine un partener, nu singura soluție, iar presiunea asupra infrastructurii publice este redusă.

Vedem acest model integrat ca pe un avantaj competitiv pentru România. În contextul în care Europa caută locații pentru dezvoltarea de capacități AI și cloud, disponibilitatea energiei verzi la scară mare este un criteriu esențial. Dacă putem oferi investitorilor un pachet integrat – teren, energie regenerabilă, stocare și soluții rapide de conectare – atunci putem transforma hub-urile energetice în poli digitali.

Pentru Monsson, această extindere nu înseamnă ieșirea din zona noastră de expertiză, ci valorificarea ei într-un mod mai complex și mai eficient. Credem că viitorul infrastructurii critice este unul integrat, iar combinația dintre energie, baterii și centre de date reprezintă un pas logic în această direcție.


DCF: Dezvoltarea unui centru de date pilot de 50 MW în România este un demers ambițios. Care sunt principalele asemănări și diferențe între dinamica investițiilor în energie regenerabilă și cea în centre de date – din perspectivă de reglementare, finanțare și scalabilitate?

 

Sebastian Enache: Dezvoltarea unui centru de date pilot de 50 MW este, într-adevăr, un pas ambițios, însă din perspectiva noastră el se bazează pe o fundație solidă. Capacitatea de conectare la rețea de 50 MW o avem deja prin proiectul nostru hibrid de la Mireasa, unde operăm 50 MW eolian, 35 MW fotovoltaic și aproximativ 200 MWh de baterii. Această combinație ne oferă condiții ideale pentru a susține un centru de date cu consum mare, în mod sigur și pe termen lung.

Din perspectiva asemănărilor, atât investițiile în regenerabile, cât și cele în centre de date sunt intensive în capital, depind de accesul la rețea și necesită predictibilitate legislativă și contractuală pentru a fi finanțabile. În ambele cazuri, investitorii caută stabilitate a cadrului de reglementare, vizibilitate asupra veniturilor și un orizont clar de dezvoltare.

Diferențele apar în dinamica tehnologică și în cadrul de reglementare. Energia regenerabilă beneficiază astăzi de un cadru legislativ matur, în timp ce pentru centrele de date nu există încă o legislație specifică sau zone clar definite unde dezvoltarea să fie prioritizată. De aceea, ne dorim să colaborăm activ cu autoritățile pentru a contribui la crearea unui cadru predictibil și competitiv.

Ne implicăm în această zonă pentru a sprijini dezvoltarea industriei locale de centre de date și, așa cum am fost pionieri în proiecte mari de energie regenerabilă, ne dorim să fim printre primii care construiesc un model integrat și în această industrie.


DCF: Proiectul pilot de 50 MW este doar începutul sau reprezintă un model replicabil? Ce planuri aveți pentru a transforma această inițiativă într-o platformă de extindere mai largă în regiune?

 

Sebastian-Enache

Sebastian Enache: Proiectul pilot de 50 MW nu este un demers izolat, ci începutul unui model replicabil pe care dorim să îl extindem la nivel național și regional. Strategia noastră vizează dezvoltarea unor centre de date cu capacități între 50 MW și 200 MW în 7 zone strategice ale României, printre care Constanța, Satu Mare și Arad. Alegerea acestor locații are la bază atât accesul la infrastructură energetică solidă, cât și poziționarea geografică și conectivitatea la rețelele de transport și fibră optică.

Obiectivul nostru este să construim o platformă integrată, în care energia regenerabilă, stocarea prin baterii și consumul mare – reprezentat de centrele de date – să funcționeze într-un ecosistem optimizat. Modelul dezvoltat la 50 MW poate fi scalat natural la 100 sau 200 MW, folosind aceeași logică: producție locală de energie, capacitate de stocare și infrastructură pregătită pentru extindere etapizată.

Dorim să valorificăm poziția geopolitică strategică a României. Deși în prezent majoritatea centrelor de date sunt concentrate în Europa de Vest, vedem semnale clare că Europa Centrală și de Est, inclusiv România, pot deveni un hub relevant pentru AI, cloud și infrastructură digitală. Prin această platformă, ne propunem să poziționăm România ca un punct central în noua hartă digitală a Europei.


DCF: Care sunt cele mai mari provocări pe care le anticipați în integrarea centrelor de date cu rețelele existente de energie regenerabilă și stocare – din punct de vedere tehnic, operațional sau de reglementare?

 

Sebastian Enache: Provocări există și vor exista întotdeauna atunci când vorbim despre infrastructură critică la scară mare. Integrarea centrelor de date cu rețelele existente de energie regenerabilă și stocare aduce atât oportunități, cât și provocări tehnice, operaționale și de reglementare.

Din punct de vedere tehnic, principala provocare este capacitatea rețelei și gestionarea fluxurilor de energie într-un mod stabil și predictibil. Centrele de date, în special cele dedicate AI sau cloud, au un consum mare și constant, iar rețeaua trebuie să poată susține aceste sarcini fără a crea dezechilibre. Totuși, un avantaj major este că proiectele regenerabile existente sunt deja racordate și, în multe cazuri, includ sisteme BESS. Acest lucru creează premisele pentru co-locarea centrelor de date lângă capacități de producție și stocare, reducând presiunea asupra infrastructurii publice și oferind o soluție mai eficientă decât în multe alte țări.

Operațional, provocarea este integrarea inteligentă a producției regenerabile intermitente cu profilul de consum al centrului de date. Aici intervin bateriile și sistemele avansate de management al energiei, care pot asigura flexibilitate, redundanță și optimizare a costurilor.

Din perspectivă de reglementare, autorizarea rămâne un punct critic. În prezent, nu există un cadru dedicat care să trateze integrat dezvoltarea de centre de date în proximitatea hub-urilor energetice. Este nevoie de claritate, predictibilitate și proceduri accelerate pentru proiectele strategice.

În ceea ce ne privește, venim cu o parte din soluție: capacitate de racordare deja disponibilă, tehnologie matură, investiții asumate și teren pregătit pentru dezvoltare. Restul depinde de colaborarea cu autoritățile și de apetitul investitorilor de a valorifica această oportunitate.